Specializing in Distributed Control Systems for power generation turbines with 10+ years of industry experience across multiple power plants.
I'm a dedicated Turbine DCS Engineer with over 10 years of experience in designing, implementing, and maintaining control systems for power generation turbines across multiple plants in India.
My expertise spans across various DCS platforms including Yokogawa, Emerson, and Siemens systems, with hands-on experience in turbine operation, maintenance, and performance optimization.
Seeking challenging roles where I can utilize my talents while learning and growing with the organization.
Diploma in Mechanical Engineering from M.B.N.I.E.T. Nizanabad Azamgarh (U.P.B.T.E.) with CCC and DCA certifications (2014)
Operation & Maintenance of Turbines, performance monitoring, and ensuring safe operations through accurate metric recording.
CCC (DOEACC), DCA (M.S. Office, Excel)
Location: Triveni Alco Chemical complex, Muzaffarnagar UP (Distillery Plant)
Plant Capacity: 1x5.44 MW Condensing cum extraction & 1x2 MW Back Pressure Turbine
Turbine: 9350 RPM, Pr. 43.0 KG, Temp. 395°C (Triveni Turbine)
Boiler: 1x60 TPH, Pr. 45KG, Temp. 400°C (Slope fired travelling grate boiler) KCP Boiler
Location: Dhanaura, Amroha, UP
Plant Capacity: 30 MW Power Plant (Cogen)
Turbine: 1X 30 MW SHIN NIPPON, RPM 4216, Pr. 102, Temp. 535°C
Boiler: 1 X 170 TPH JIT Boiler (Travelling Grate)
DCS: Yokogawa
Location: Pata, Auraiya UP
Contractor: Prabha Continous Utility Services Pvt Ltd
Plant Capacity: 59 MW Power Plant
Turbine: 2X 25 BHEL Turbine (Condensing), RPM 5050, Pr. 105, Temp. 505°C
Boiler: 2 X 170 TPH ISGEC Boiler (Gas Fired)
DCS: Emerson
Location: Bhuj, Kutch, Gujarat
Contractor: Pratim Consultant & Energy Pvt Ltd
Plant Capacity: 4.99 MW Thermal Power Plant
Turbine: MAN Diesel & Turbo India Pvt Ltd, RPM 7552, Pr. 65 Kg, Temp. 485°C
Boiler: 2*27 TPH AFBC Boiler (Thermodyne Engineering)
Location: Satahariya, Jaunpur, UP
Plant Capacity: 1 X 60 MW Captive Power Plant
Boiler: Wuxi Huaguang Boilers Co. Ltd., China, 1 X 240TPH CFBC
Turbine: Nanjing turbine & electric machinery, RPM 3000, Pr. 8.8 Mpa, Temp. 535°C
DCS: Emerson
Location: Satahariya, Jaunpur, UP
Location: Satahariya, Jaunpur, UP